
Our inaugural podcast covers a piece of highly charged news: the preliminary verdict from the Department of Commerce on the Anti-Dumping (AD) complaint which resulted in a 31 percent levy for most of the major Chinese panel manufacturers. We covered the verdict yesterday, as well as feedback from both sides of the dispute. Here's the text of the Department of Commerce fact sheet.
In today's podcast, Scott Clavenna, Greentech Media's CEO, leads a brief discussion on the short- and medium-term effects of the preliminary ruling and the story angles GTM will cover in the coming weeks.
We look forward to providing these podcasts as a regular feature and bringing you the events of the week in a different format. You'll hear from GTM research analysts, editors, reporters and the occasional special guest. Stay tuned.
- Login or register to post comments
- Feed: Greentech Media
- Original article

The U.S. Department of Commerce (DOC) levied a second round of preliminary tariffs against Chinese solar module imports in the ongoing trade war between U.S. solar manufacturers and their Chinese counterparts. The following are the anti-dumping tariffs handed down in the ruling:
- Suntech: 31.22 percent
- Trina: 31.14 percent
- Named Chinese firms: 31.18 percent
- Firms that did not provide info to Dept. of Commerce: 249.96 percent
These anti-dumping tariffs will be compounded by the countervailing duties that the DOC levied on March 20. The countervailing duties are listed below:
- Suntech: 2.90 percent
- Trina: 4.73 percent
- Everyone else: 3.59 percent
The following is a series of comments from GTM Research’s Senior Analyst, Shyam Mehta on how the tariffs will affect Chinese suppliers in the U.S.
- “While the margins are not as high as those seen in many previous U.S.-China antidumping cases (electrical blankets, steel grating), they are certainly much higher than Chinese manufacturers would have hoped for,” said Mehta. “Stacked onto the margins for countervailing duties, they amount to levels of 35 percent to 36 percent, which is significant.”
- “Keep in mind that this is a preliminary decision. We expect Chinese manufacturers and CASE representatives to contest the findings in the days ahead.”
- “The margins were obviously driven in part by the Department of Commerce’s choice of the ‘proxy economy’ to estimate costs, as China is considered a ‘non-market economy.’”
- “At these margins, China-based manufacturers would certainly have to raise U.S. prices to turn a profit. It is not feasible for them to maintain prices at tariff-free levels and still be profitable. In the short term, this is likely to lead to module price increases in the U.S. which would serve to dampen demand and installation growth. If the Chinese were to absorb the tariff, it would place their costs close to parity with many U.S.-based suppliers.”“However, Chinese firms are hardly likely to stand still. Broadly speaking, they have two strategies: set up cell manufacturing outside China, or use the tolling services of Taiwan-based suppliers to turn wafers into cells there, and then assemble the modules in China. Both strategies would allow the Chinese to bypass import tariffs. We estimate that tolling cells to Taiwanese firms would increase Chinese costs by 6 percent to 12 percent, which is meaningful but manageable.”
- “Given this, we do expect that the decision will result in at least incremental investment in domestic manufacturing by Chinese firms. However, there are other, lower-cost manufacturing locations that these firms could set up manufacturing in, such as Mexico and Taiwan, for example that would still allow them to price their modules below that of U.S.-based suppliers. Therefore, we see the impact of this decision on U.S. manufacturing as positive, but spurring limited investment in the future and likely only temporary relief for existing U.S.-based suppliers.”
For further reading on the trade case from GTM Research and Greentech Media, visit here, and to read the Department of Commerce fact sheet, go here.
- Login or register to post comments
- Feed: Greentech Media
- Original article
Now that AMI has become more of a steady-state business in the U.S., Gary High from Landis+Gyr talks about growth opportunities in emerging markets and innovation with utilities in the U.S.
- Login or register to post comments
- Feed: Greentech Media
- Original article

If, as currently predicted, Southern California Edison is unable to get its 2,200-megawatt San Onofre Nuclear Generating Station (SONGS) back in service in time for the heat of the summer, California’s power generation and delivery system will be profoundly tested.
“An extended outage of both SONGS units may create local reliability issues during heat waves for San Diego and parts of south Orange County,” the California Independent System Operator Corporation (CAISO) said. “Parts of the grid serving the Los Angeles Basin may also be stressed during high demand periods.”
To meet Southern California’s demand for electricity without hamstringing its economy, the ISO is making plans that will put into action idled power plants, new transmission, the state’s best practices, renewables and cutting edge grid tools.
“Southern California Edison’s four replacement steam generators at their San Onofre Nuclear Generating Station failed in less than two years of operation, while the original equipment operated for 28 years,” noted a just-released Fairewinds/Friends of the Earth report.
SCE has, according to the Fairewinds report, acknowledged replacing the steam generators as “a strategic decision to avoid a more thorough license amendment and review process” by the Nuclear Regulatory Commission (NRC).
The right solution to the vibration problem that led to the shutdown, according to Fairewinds, requires “major modifications with repair and outage time that could last more than eighteen months if Edison and Mitsubishi are even able to repair these faulty designed steam generators,” adding, “the safest long-term action is the replacement of the San Onofre steam generators.”
While SCE continues to work with the NRC to bring SONGS back, the ISO is working to minimize impacts.

“We are not the safety experts. That’s the NRC,” said ISO Director of Communications and Public Relations Stephanie McCorkle. “Our job is to plan.”
The ISO is, McCorkle noted, doing “contingency planning in coordination with the Governor’s office, state energy agencies, federal officials and the utilities [because the loss of SONGS] reduces local electricity supply and the ability of the high voltage grid to import power into the region that already has limited transmission lines.”
McCorkle was blunt. Without contingency planning and mitigation of that 2,200-megawatt loss, she said, “We would be in the hole.”
The focus of the ISO’s planning has been two gas-fired power plant units previously closed as a result of the state’s efforts to clean up its power supply and two under-construction transmission lines.
The ISO considered it “absolutely critical to get units three and four at the Huntington Beach Power Plant available for dispatch, and that was done as of Friday,” McCorkle said.
“The Huntington Beach units not only add 452 megawatts of capacity in the LA Basin,” the ISO reported, “but also enable 350 megawatts of additional imported power to transfer into San Diego.”
Bringing these units back will cost SCE and San Diego Gas and Electric (SDG&E) $2.5 million per month. Air quality regulators have permitted their service through November 1.
Completing the Sunrise Powerlink and Barre-Ellis transmission lines on schedule in June, before the summer’s peak demand hits, McCorkle said, will “strengthen the transmission system in general and allow us to import more power from the Southwest.”
Without these mitigations, McCorkle said, the LA Basin would be short 240 megawatts on a high-demand, hot day and the San Diego area would be short 337 megawatts. With them, she said, we only have reserve margins of thirteen megawatts in San Diego and of 212 megawatts in the LA Basin.
The ISO has also secured $9 million in funding from the California Public Utilities Commission (CPUC), McCorkle said, to reactivate its Flex Alert conservation campaign. Radio and TV ads will begin appearing in late June that will teach consumers conservation measures for Southern California’s 4 p.m. to 6 p.m. “air conditioner rush hour,” when load is most likely to exceed ISO capacity.

Finally, McCorkle said, the ISO and the utilities are “encouraging more participation in local voluntary demand response (DR) programs.” As a result, recent SCE and SDG&E smart meter programs may pay off sooner and bigger than expected in heading off rolling power outages.
“Because SDG&E has 100 percent smart meter penetration,” McCorkle said, “it can track how much customers are cutting back.” Customers who conserve will, for the first time in California, be compensated without having to enroll in a program. It is “a way for people to respond and be compensated,” she explained. And conserved energy, she added, “is counted like any other resource. This is where people power is going to pay off.”
The ISO is also, McCorkle said, “analyzing the potential long-term implications of being without the San Onofre units.” Its conclusion, she said, is “there aren’t adequate resources to replace San Onofre permanently. We’re just trying to fill the holes as best we can."
This video was part of the ISO's last Flex Your Power campaign.
- Login or register to post comments
- Feed: Greentech Media
- Original article

The Insurance Institute for Highway Safety busted up a few Prius C hybrids to see how they held up in crashes. Here's what they found...
- Login or register to post comments
- Feed: TreeHugger
- Original article

Could a combination of alligator farming and hydroponics be the savior of former chicken farmers, or is it a dangerous and cruel distraction?
- Login or register to post comments
- Feed: TreeHugger
- Original article

Watson must put up over $300,000 in bail and stay in Germany while awaiting the final ruling on whether he will be sent to Costa Rica to face trial on a decade-old charge.
- Login or register to post comments
- Feed: TreeHugger
- Original article

It seems like it was just yesterday that Lexus introduced the HS 250h hybrid, the first dedicated luxury hybrid (like the Prius, there's no non-hybrid version of the HS 250h).
- Login or register to post comments
- Feed: TreeHugger
- Original article

In signing the ban into law, Vermont's governor reminds us that there was civilization before fossil fuels, but there was no life at all before water.
- Login or register to post comments
- Feed: TreeHugger
- Original article

Apple has announced that its Maiden, NC data center will be fully powered by renewables and that its solar power installation there will now be twice as big as first planned.
- Login or register to post comments
- Feed: TreeHugger
- Original article
